RBX/FRA/LDN - Hardware Upgrades
Scheduled Maintenance Report for CubedHost, LLC
Completed
The scheduled maintenance has been completed.
Posted 24 days ago. Mar 29, 2019 - 04:55 UTC
Verifying
Frankfurt, DE & London, UK are complete. We will proceed with the Montreal, CA migrations to remain on-time, then we will re-verify the transfer status of all transferred systems this evening.

Our automated systems show that all systems were successfully transferred and that all IPs are online.

Please reach out to our team if this is not the case for your server(s).
Posted 24 days ago. Mar 29, 2019 - 03:24 UTC
Update
Roubaix, FR is complete.
Posted 24 days ago. Mar 29, 2019 - 01:58 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted 24 days ago. Mar 29, 2019 - 00:00 UTC
Update
With the exception of London nodes 8 and 10, all other nodes in the region will be updated this evening. We are still awaiting the equipment for these two systems. London node 10 will be renumber to London node 7 to fill the gap from previous hardware upgrades. A later maintenance will be scheduled for nodes 8 and 10 appropriately.
Posted 24 days ago. Mar 28, 2019 - 22:49 UTC
Scheduled
The CubedHost Operations team has scheduled an additional maintenance continuing on yesterday's maintenance windows in order to further complete our hardware upgrades. The majority of the additional systems have been received and we'll be upgrading as many systems as possible this evening.

One final maintenance window may be scheduled, pending on the amount of systems that remain to be upgraded, likely after the 1st of April.
Posted 24 days ago. Mar 28, 2019 - 20:00 UTC
This scheduled maintenance affected: Minecraft: Java Edition (Frankfurt, DE, London, UK, Roubaix, FR).